Building Committee
Minutes
Wednesday December 12, 2007, 4pm Meeting #12 in Church
Present: Building Committee
members Fr. Bajorek, John Bowie, Tom Felton, Jane Banik and Ken Margolis along
with invited guests, Fr. Yetman, Deacon Vadino, John Spinelli, Paul Fraatz,
Rosemary Endres, Mike Keller, Doug Nagle (TomÕs assistant) and Frank King.
v
Minutes from the October
9th meeting were previously approved by email consensus and posted on our Web
Site.
12A.
KM Presented a brief overview of the Building CommitteeÕs work since our first meeting on
March 20th with emphasis on the Sanctuary and considerations
pertaining to the relocation of the Blessed Sacrament Altar (BSA) and the Ambo.
Our objective at this meeting is to determine possible new locations for the
(BSA) and the Ambo utilizing the mock ups that will allow a visual and help us
to better understand and eventually confirm the proposed new locations.
12B.
The Blessed Sacrament Altar mock up was placed behind the main Altar and once
again this location felt natural to all in attendance with the only
consideration to possibly adjust the height of the Tabernacle.
12C.
The Ambo mock up was viewed in various locations and a lengthy conversation
ensued resulting in our selection of three possible new locations. The first
and what is currently viewed as the most cost effective location is in front of
the presiders chair with or without a step up (location #1 on the attached
photo). The second and third locations are as illustrated on the attached photo
marked location #2 and #3, both requiring a marble extension of our main Altar
area.
12D.
To help us determine which if any of these three locations are right for us, we
will prepare scaled renderings and study alternative designs of a new Ambo and
re-group when this work has been completed.
12E.
Rich McCartney of Lighting Solutions in Media submitted a detailed lighting scheme
and reviewed their recommended lighting solution to accommodate our new ceiling
design while addressing our concern and objective to ensure the new lighting
will enhance our Liturgies and provide even lighting throughout the church
interior, Sacristy, vestibule, stairwells and provide accent lighting to our
windows, statues and stations of the cross.
Samples
were set up and viewed and to allow us to finalize the proposed scheme, Rich
will make up a light grid that will be elevated on a stand to simulate the
proposed lighting and at a date to be determined, we will view this simulation
in our Church.
Rich
will also complete the bill of material and reconfirm total wattage as compared
to our existing wattage.
Tom
will be coordinating this effort.
12F.
Tom presented samples of the selected acoustic panel and wood veneer beam
designs.
v
Next Steps:
á
BCMÕs to complete action
items as stated above and as pending from previous meetings.
á
The Pre-Bid session is
scheduled for Monday December 17th at 10am. Eight out of ten General
Contractors invited are expected to be present. The format will include a
presentation of our project, the hand out of a pre-bid package containing
detailed documentation as it currently exists and a walk through of the areas affected
by the planned renovations. Pre-bids are requested to be submitted to us within
a month after our meeting.
á
The Building Committee
members will meet at a date to be determined.
á
ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ..Submitted
by KM