Building Committee
Minutes
Tuesday July 31, 2007, 5pm Meeting #9 in Parish House
Conference Room
Present: Building Committee
members Fr. Bajorek, John Bowie, Tom Felton and Ken Margolis along with invited
guests, Rosemary Endres, and Mike Keller.
v
Fr. Bajorek opened the
meeting with a prayer.
v
Minutes from the July
10th meeting were previously approved by email consensus.
9A. We discussed the gym
renovation and confirmed the following:
á
The project is on
schedule and at budget.
á
John B will follow up on
pending items due from Miller to complete their contract.
á
John B. will obtain from
Miller the recommended use and maintenance guidelines and work with John Spinelli
to complete a user/maintenance guideline document.
á
The re-opening and
Blessing date was discussed and the expedited target date of August 12th
may not allow enough time to ensure the gym is completed to a safe environment,
so a re-open announcement will be determined at a later date.
á
New folding chair sample
was approved for ordering of two support racks that will hold 84 chairs each.
á
The new kitchen folding
access partition door was approved for ordering.
á
The optional floor
covering system will not be ordered at this time and future consideration will
be given to its purchase and/or a rental if deemed necessary.
á
A new floor cleaning
machine was discussed, no decision at this time.
á
A walk through of the
gym was conducted by those in attendance.
9B. Tom presented an extensive
time line and required action items document which was the focus for the
remaining part of the meeting and the following key points were agreed upon.
9C. The project has been
broken down into four major categories including, A-Front entrance and traffic
flow improvements, B-Church ceiling and interior, C-Church elevator and D-Overall
Campus and school improvements; all of which have individual item requirements
and an estimate of time for design development, product research, parish
presentation feedback, construction documents and final completion.
9D. Projects B and C will be
the initial priority focus and Tom was given approval to proceed with outside
consultants as required.
9E. Tom will lead the effort
of expediting the work necessary while utilizing Building Committee members as
needed and keep the entire committee informed of progress between meetings.
9F. John B. will discuss the
proposed pre-bid with general contractors and separate bids from sub
contractors; (SJC proposed bid process) with Fr. Vogan and seek his approval.
9G. John B will obtain a GC
and SC list from Jack and Ernie.
9H. We discussed the idea of
acknowledging SCJ parishioners who have provided work and material for the gym
renovations, as well as asking to hear from other parishioners (contractors) that
may have interest to learn more about the project in an effort to seek their
interest of involvement.
9I. We agreed to do the necessary
due diligence to determine the use of a project manager versus the use of a
general contractor.
9J. We agreed to do the necessary
due diligence to determine whether or not the church can remain open for
weekend Mass during the renovations versus the complete shut down.
9K. We discussed the
importance of continued communication to our fellow parishioners, bulletin,
pulpit, web site and the possibility of a town meeting to present the plans
once developed.
v
Next Steps:
á
BCMÕs to complete action
items as stated above and as pending from previous meetings.
á
The Gym project
management team will meet separately as required and coordinated by John Bowie
through completion.
á
Tom will coordinate
individual meetings/phone conferences with BCMÕs as required to expedite the
timeline action items.
á
The Building Committee
members will meet on Tuesday August 21st at 5pm in the Parish House
á
ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ..Submitted
by KM