Building Committee
Minutes
Friday March 14, 2008, 5pm Meeting #16 in the Parish
House
(Revision 1)
Present:
Building Committee members Fr. Bajorek, Tom Felton, Jack Quindlen, John Bowie,
John Brennan, Ernie Menold, Jane Banik and Ken Margolis. Not present: Rosemary Endres.
Also
present: Doug Nagle (from Tom FeltonÕs office)
16A. The Committee agreed to the following:
1.
Tom F should
proceed with preparing the drawings and specifications for a project that
contains a fully-detailed exterior cupola (lantern) and no alternates.
Tom F presented a budget to the committee that
includes a lantern in the design – and he believes the bids will come
back within our budget, including the lantern. He also advised against adding alternates to the drawings
and specifications in order to: 1) keep the bidders focused entirely on the
committeeÕs principal project goals, and 2) maintain the project
timetable. Based on this
information, the committee agreed to proceed with a design containing a
fully-detailed exterior cupola (lantern) and no alternates.
2.
The design of the
nave/sanctuary ceiling will contain either ArmstrongÕs ÒOptimaÓ or ÒUltimaÓ
pressed mineral fiber, removable panels, hung in a concealed grillage system
that utilizes a portion of the existing slab-hung supports. The final acceptance of the Armstrong
product, however, is subject to visits to in situ installations to inspect and
approve the look as relevant to our building. Tom FÕs ÒArmstrong Option 1Ó was selected as the design to
be placed in the drawings and specifications. The ÒDecousticsÓ and ÒSimplexÓ ceiling products have been
eliminated from the project.
3.
Tom FÕs drawings
and specifications should be completed and ready to distribute to the three (or
possibly four – if Pancoast & Clifford are still interested)
pre-selected General Contractors on or before April 7, 2008.
4.
Tom F will create
a bid form that calls for a single bid price for the project in its
entirety. However, within the bid
form, there will be individual line items for each bidder to disclose their
labor and material costs for such tasks as the lantern, the ceiling, the
lighting, the elevator, and so on.
5.
Tom F will
establish the due date for the bids to be Friday, April 18, 2008. On that date, project architect Tom F,
building committee leader Ken M and Fr. B will open them at the Archdiocesan
offices in Philadelphia.
6.
To the extent
that the bids received exceed the amount of funds available for the scope of
work designed, the Committee will enter into negotiations with any or all bidders
in an attempt to reduce/adjust the project scope and cost to meet the funds
available in order to make an award and proceed to the contract signing.
It is important for all building committee members to
bear in mind, as Fr B has expressed on several occasions, that the published
purpose of this capital campaign is to accomplish several ÒbigÓ projects (the
gym floor, the ceiling in the church, the handicapped parking and front entry
plaza, the required liturgical changes and the elevator) and, at the same time,
to repair and update the 40 year old church building, as well as attending to
the parish grounds. As Fr. B has
also noted, the Òrepair and updateÓ of the church building is as important as
the ÒbigÓ projects.
Finally, Fr. B provided clear direction to the
committee that he is in favor of adding the lantern to the church building only
as long as it can be done without compromising the quality of the projects the
capital campaign was initiated to accomplish. Fr. B stated that the lantern is beautiful and that he
genuinely hopes the bids received do not exceed the amount of funds available.
7.
Construction will commence in summer
2008 (most likely in August) – and proceed so that a late-November or
early-December 2008 completion date can be achieved. The work schedule will be configured so that all demolition
associated with the elevator portion of the work is completed before school
resumes in early September, so as to keep the amount of disruption to classes
to a minimum – especially regarding loud demolition noises, dust
creation, and blocking of exits.
8.
Fr. B will notify
the August 2008 wedding parties of the schedule, so they can proceed with
making their alternate arrangements.
16B. Two
possible elevator schemes were also discussed – but only peripherally
(not all committee members heard or participated in the discussion). Tom F and John Bo presented two sheets
showing: 1) the first floor of the narthex, and 2) the basement of the Lower
Church Hall directly beneath the narthex.
The left-hand side of each page contains Option 1 and the right-hand
side of each page contains Option 2.
Option 1 places the LuLa elevator in the center of the existing
stair-hall – thus necessitating removal of the existing stair and
installation of a new steel pan stair.
It also necessitates slight/limited reconfiguration of the classroom and
kitchen directly below. Option 2
places the LuLa elevator in the area of the second toilet room upstairs and in
the center of the girlÕs rest room downstairs – thus requiring the
complete reconfiguration of the upstairs toilet room, plus the loss of the
upstairs janitorÕs closet and the loss of two girlÕs toilet stalls
downstairs. Option 2 will also
necessitate a lot of piping work, plus a lot of tile floor and wall finish work,
which is significantly more expensive than replacing a steel stair. More important, however, is the subtle
aspect of user dignity – the LuLa shown in Option 1 enables the user to
enter using forward motion, and exit using forward motion. The LuLa in Option 2 requires the user
to enter using forward motion but exit backing out – which is demeaning.
Although
this issue was not discussed by the Committee as a whole at the meeting, it
seems apparent to Tom F and John Bo that Option 1 is superior in all aspects
– and in the interest of time, Tom F will proceed with placing said
option into the drawings and specifications. Committee members are requested to post your thoughts
– especially if there are contrary opinions, as soon as possible.
Incidentally,
the term ÒLuLaÓ stands for limited use, limited access elevator. It is not an elevator in the
traditional sense – it is intended for use exclusively by a disabled
person and one companion (care giver).
It is not for general convenience or for freight use.
16C. Several
other activities took place this past week, which committee members should be
apprised of, but which were not discussed at the meeting (they are presented
herewith to keep everyone up-to-date on everything taking place):
1. In a meeting on Tuesday, March 11, 2008 with eminent
lighting designer Edwin Rambusch and lighting supplier Rich McCartney, the
concept of installing exterior and interior lights to accentuate the stained
glass windows at evening-time during occupancy and evening-time while empty (respectively)
was nixed. It seemed like a good
idea at the time – but in practicality, it would generally only produce
hot-spots on the glass and not uniformly illuminate the windows in a manner
similar to sunlight. However, an
exception to this is the stained glass window of the Resurrection over the
front doors of the church building, which is currently illuminated at night,
and should be maintained and upgraded.
2. At that same meeting, Rich McC demonstrated several
tungsten/halogen/quartz recessed ceiling light fixtures. Using the long ladder together with
John SpinelliÕs scaffolding, Rich McC and Mike Keller positioned the lights
near the ceiling and moved them around to find the area of best coverage. The color and intensity of the light
was far beyond our expectation and provided a stunningly remarkable
transformation to the aesthetic character of the space. Additional investigation will be
conducted by committee members on the quantity and placement of these fixtures,
in combination with possible decorative fixtures to be strategically placed in
the nave, in combination with new fixtures to be placed in the stair-halls.
3. Earlier that day, Brendan Doyle of Butler Roofing
Systems visited and mentioned that Butler would consider extending the churchÕs
existing metal roof warranty if the lantern contained their roofing and
flashing products. (He offered it
– but itÕs not in writing yet.)
This is an important consideration – because the buildingÕs
existing metal roof is three years beyond its original 10 year warranty, and
leaks have started to develop.
4. Also earlier that day, committee members met with
Tootsie Troiani of Kay & Sons (wall covering and window treatment
suppliers) about the possibility of installing a fabric panel system to be used
behind each of the Stations of the Cross on the rear nave walls. These panels could provide the Stations
with more identity (currently, they are fairly obscure against the brick),
especially when combined with accent lighting.
5. Also earlier that day, committee members met with two
independent sound specialists seeking their recommendations and proposals to
update the church buildingÕs sound system.
6. In the handout packets at the meeting, Tom F provided
a design for an Ambo that will match the stone and style of the existing Altar,
Baptistry and Tabernacle. The
committee did not have a chance to discuss this design, but Tom F will send it
out for pricing by the recommended archdiocesan stone specialist (Luigi?), and several
other fabricators with whom he has worked in the past.
7. Also in the handout packets at the meeting, Tom F
provided two schemes for the two west entry stair-halls – one employing
stone tiles and one employing a wood wainscot. Tom F will send these out for pricing as well.
These
Minutes submitted by John Bowie – March 15, 2008 (RV1 - March 17, 2008)