Building Committee
Minutes
Friday February 22, 2008, 3pm Meeting #15 in the
Parish House
Present: Building Committee
members Fr. Bajorek, Tom Felton, Jack Quindlen, John Bowie, John Brennan, Ernie
Menold, Ken Margolis and Rosemary Endres.
v
Minutes from the
January 29th meeting were previously approved by email consensus and
posted on our Web Site.
15A. KM presented an overview
of the three interview meetings with the selected General Contractors being considered
for SJC planned renovations. We discussed the company profiles, the interactions
with them to date, their site visits to St. JohnÕs and what we could expect from
them as far as costs and service based upon our due diligence and knowledge
gained to date.
A summary and background
information was presented to substantiate the project scope proposals that were
prepared for open discussion and eventual consensus.
Each committee member had the
opportunity to fully express their opinions, concerns and recommendations of
the three options presented and how best to proceed.
15B. After a very lengthy
discussion of the project scope, the three options presented along with logistical
and financial issues, the committee reached consensus on how best to move
forward.
15C. The committee agreed to
the following:
á
Three ceiling
design options will be finalized and become part of our definitive bid specifications,
namely; Alternative #1 utilizing our current raised ceiling design with painted
beams and external Lantern.
á
Alternative # 2
utilizing our current raised ceiling design with painted beams and lay light
dome (internal Lantern effect) in lieu of the external Lantern.
á
Alternative # 3
utilizing our current raised ceiling design eliminating the painted beams and
incorporating a one dimensional raised ceiling with the external Lantern. The
goal in all alternatives is to stay within the established budget.
á
The three
alternatives will incorporate all other assigned costs as illustrated under
ÒSuggested allowances Option OneÓ dated February 21, 2008 with the exception of possibly eliminating
the AC in the gym.
á
All maintenance
items, sound and gym readiness expense for Mass celebration will be handled outside
of the General ContractorÕs scope as well as the possibility of the Church AC
update.
15D. TomÕs firm now has
adequate project scope directives to work towards completion of the definitive
set of bid documents and committed to a completion date of April 7th,
2008.
15E. Several initiatives need
to take place to maintain the April 7th date and under separate cover,
TomÕs firm will provide this list and their recommendations of proper handling.
These items include such things, (but not limited to):
á
Meetings with
DeCoustic and alternate ceiling manufactures.
á
Further
investigation to accommodate handicap access into the Church lower level.
á
Defining the
scope of work listed under maintenance and bathrooms only to the extent that it
could be carried out simultaneously to the planned renovations.
á
Arranging site
visits to selected GC reference facilities.
á
Finalizing the
lighting and sound plans.
á
Finalizing phase
one of the site work planned and incorporating the widening of our exiting
access road as per concept drawing reviewed.
á
Maintaining
project timeline as per document submitted on this date.
15F. It was agreed that the
timeline TomÕs firm presented is aggressive, but viable and plans towards the anticipated
closing of the Church this summer will be developed.
15G. It was reconfirmed that
all planned renovations will be budgeted for maximum accomplishment while maintaining
the established budget without the necessity of a Parish loan.
v
Next Steps:
á
BCMÕs will assist
TomÕs firm as required to ensure the established timeline can be met.
á
TomÕs firm will
prepare definitive bid specifications.
á
Alternatives will
be studied to allow handicap access to the lower level.
á
The Building
Committee members will meet in task groups as required.
á
ÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉÉ..Submitted
by KM